Finland, Lohja solar park, 8.5 MWp
Customer: Helsinki Energy
Location: Lohja city, 60 km west of Helsinki, Finland
Time plan: Project start November 2023, ready for production in 2024
Eltel responsibility – Balance of System delivery including
- Weekly progress reporting
- Project management from power plant design to commissioning
- Hardware procurement and logistics of power electronics and cabling
- All installation work (mechanical and electrical) and site logistics
- Civil works
- Connections to substation and grid
- Commissioning and documentation

Sweden, Hallstavik solar park, 64 MWp
Customer: Intec
Location: Hallstavik, municipality of Norrtälje, 61 km east of Uppsala, Sweden
Time plan: Project start in Q2-2023, ready for production in 2024
Eltel responsibility – Subproject electrical works, including
Trenching and cabling
- Trenching and cabling
- All electrical installations
- Commissioning
- Electrical security responsibility for the entire solar park project

Denmark, Ølgod solar park, 55 MWp
Customer: GreenGo Energy
Location, Ølgod, Vejen, Denmark
Time plan: Project start-up August 2023, planned to be in production end of 2024
Eltel responsibility – Turnkey project delivery of substation and grid connection
- Connection to grid
- Design and project management
- Civil works
- Electrical installations LV, MV and HV of power transformer and switch gear

Denmark, Højby solar park, 55 MWp
Customer: GreenGo Energy
Location: Højby, just outside Odense, Denmark
Time plan: In production since August 2023
Eltel responsibility – Subproject responsibility transformer mounting and grid connection
- Mounting of UPS and SCADA
- Project management incl. contacts with DSO and other contractors
- Mounting of end terminations on transformer and PV substation