Finland, Lohja solar park, 8.5 MWp

Customer: Helsinki Energy

Location: Lohja city, 60 km west of Helsinki, Finland

Time plan: Project start November 2023, ready for production in 2024

Eltel responsibility - Balance of System delivery including

  • Project management from power plant design to commissioning
  • Hardware procurement and logistics  of power electronics and cabling
  • All installation work (mechanical and electrical) and site logistics
  • Civil works 
  • Connections to substation and grid
  • Commissioning and documentation
  • Weekly progress reporting

Denmark, Ølgod solar park, 55 MWp

Customer: GreenGo Energy

Location, Ølgod, Vejen, Denmark

Time plan: Project start-up August 2023, planned to be in production end of 2024

Eltel responsibility - Turnkey project delivery of substation and grid connection

  • Design and project management
  • Civil works
  • Electrical installations LV, MV and HV of power transformer and switch gear
  • Connection to grid

Sweden, Hallstavik solar park, 64 MWp

Customer: Intec

Location: Hallstavik, municipality of Norrtälje, 61 km east of Uppsala, Sweden

Time plan: Project start in Q2-2023, ready for production in 2024

Eltel responsibility - Subproject electrical works, including

  • Trenching and cabling
  • All electrical installations
  • Commissioning
  • Electrical security responsibility for the entire solar park project




Delivered projects

Denmark, Højby solar park, 55 MWp

Customer: GreenGo Energy

Location: Højby, just outside Odense, Denmark

Time plan: In production since August 2023

Eltel responsibility - Subproject responsibility transformer mounting and grid connection

  • Project management incl. contacts with DSO and other contractors
  • Mounting of end terminations on transformer and PV substation
  • Mounting of UPS and SCADA